References

Evergy

818 S. Kansas Avenue

Topeka, Kansas

Mr. Pat Tryon

Facility Architect

785-575-8206

Greater Topeka Partnership

719 S. Kansas Avenue, Suite 100

Topeka, Kansas

Mr. Matt Pivarnik

Director

785-234-2644

Kansas State University Housing & Dining Services

L.W. Davenport Building

Manhattan, Kansas

Mr. Skyler Harper

Associate Director, Housing Maintenance

785-532-6466

Sheltered Living

3401 SW Harrison

Topeka, Kansas 66611

Mr. John Ratzenberger

VP of Development

785-266-8686

TranSystems

2400 Pershing, Suite 400

Kansas City, Missouri

Ms. Bonnie Holthaus

816-329-8600

University of Kansas

113 Strong Hall, 1450 Jayhawk Boulevard

Lawrence, Kansas

Mark Reiske

Director Facilities Planning and Development

785-864-5644

Project References

Evergy

818 S. Kansas Avenue

Topeka, Kansas

Mr. Pat Tryon, Facility Architect

Project Date:
2000 – Present

Scope:
At 15 locations – 800 workstations, over $7M in design work

Command and General Staff College

100 Stimson Avenue

Lewis & Clark Center

Fort Leavenworth, Kansas

Roberta Proctor, Project Manager

Allan Bockrath, Director of Logistics

Contract Award #W91QF4-06-R-0014

Project Date:
2007 – Present

Scope:
Building 120 – Approx. 300 offices/workstations, etc.

U.S. Department of Housing & Urban Development

400 State Avenue

Kansas City, Kansas 66101

Scope:
HUD remodeled four floors of existing space in 12 phases. This included new flooring, fresh paint and furniture by Kimball and National Office Furniture. The furniture was shipped six months before the space was ready due to Federal funding restrictions. Furniture for 240 HUD employees was sorted and stored by phases then delivered in monthly installments over the next year.

Kansas Statehouse

700 SW 10th Street

Topeka, Kansas

Barry Greis, Statehouse Architect

Project Date:
2006 – Present

Scope:
Approximately 200 private offices

U.S. Army Corps of Engineers

Kansas City, Missouri

John Hunt

Project Date:
Installed Fall of 2009

Scope:
Approximately 30 private offices

MARS Chocolate North America

Topeka, Kansas

Ashley Teel, Associate Project Engineer

Project Date:
2013

Scope:
105 Workstations and Administrative area

Wichita Readiness Center

Kansas Army National Guard

2800 SW Topeka Boulevard

Topeka, Kansas

Cpt. Michael Liotta, Project Manager

Project Date:
Installed: Summer/Fall 2013

Scope:
Scope: Approx. 120 workstations, 65 private offices, 150 training tables, 25 meeting areas and multiple workrooms